How many days will it take for 4 men to complete a job that 6 men can complete in 8 days, assuming equal work rate?

Prepare for the Senior Sewage Treatment Worker Test with our flashcards and multiple choice questions, featuring hints and detailed explanations. Excel on your exam!

To determine how many days it will take for 4 men to complete a job that 6 men can complete in 8 days, we first need to calculate the total amount of work represented in man-days.

If 6 men can finish the job in 8 days, we can find the total work in man-days by multiplying the number of men by the number of days they work. Thus, the total work is:

Total Work = Number of Men × Number of Days = 6 men × 8 days = 48 man-days.

Now, we need to find out how many days it will take for 4 men to complete the same amount of work. To find this, we divide the total work by the number of men who will now be working:

Time = Total Work / Number of Men = 48 man-days / 4 men = 12 days.

This calculation shows that it will take 4 men 12 days to do the same amount of work that 6 men can complete in 8 days, assuming that all men work at the same rate.